Skip to main content

PMP Exam Formulas



PMP exam gets it fair share of formula based numerical problem solving questions. Memorizing these formulas will help you handle these questions during PMP exam.



EV = %Complete*BAC

AC = %Spent*BAC

CV = EV–AC (>0 Good)

SV = EV–PV (>0 Good)

CPI = EV/AC (>1 Good)

SPI = EV/PV (>1 Good)

EAC = AC+Bottom up ETC – Best however team has to stop working and spend time

EAC = AC+BAC–EV - Remaining work to be performed at budgeted rate

EAC = BAC/Cumulative CPI - Remaining work to be performed at present CPI

EAC = AC+(BAC–EV)/(Cumulative CPI*Cumulative SPI) - Remaining work to be performed at present rate involving both SPI and CPI

ETC = EAC–AC or Re-estimate

VAC = BAC–EAC

TCPI = (BAC-EV)/(BAC-AC ) or (EAC–AC) – EAC will be used once it is determined BAC is no longer achievable, less then 1 is good

PV = FV/(1+r)n

Communication Channels = n(n-1)/2

EMV = P*I

PERT EAD = (O+4M+P)/6

PERT Project Duration = Sum of PERT EADs

SD = (P-O)/6

Variance of Activity =  [SD]2 = [(P-O)/6]2

SD of Project = Square Root of Var1 + var2 + ......

Range of activity duration = EAD +/- SD

Total Float/Slack = LS-ES or LF-EF - zero on critical path

BCR/IRR/NPV – Bigger is better

Mean – Average

Median – Center number/value or average of center values

Mode – The most frequent number

Contract Incentives Savings = Target Cost – Actual Cost

Bonus = Savings x Percentage

Contract Cost = Bonus + Fees

Total Cost = Actual Cost + Contract Cost

PTA = (Ceiling Price – Target Price)/Buyer’s Share ratio +Target Cost



Terms Used

Planned Value (PV)

Actual Cost (AC)

Earned Value (EV)

Budget At Completion (BAC)

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI)

Schedule Performance Index (SPI)

Estimate at Completion (EAC)

Estimate to Complete (ETC)

Variance At Completion (VAC)

Probability (P)

Impact (I)

Expected Monetary Value (EMV)

Expected Activity Duration (EAD)

Standard Deviation (SD)

Late Start, Early Start, Late Finish, Early Finish (LS, ES, LF, EF)

Point of Total Assumption (PTA)

To Complete Performance Index [TCPI]

Comments

  1. Suchit Kumar KMay 16, 2010 6:56 PM

    I would like to receive PMP formulas to my mail.

    ReplyDelete
  2. Dear Sir,

    I would be grateful if you kindly provide all the applicable formulas for the PMP exam.

    Warm Regards,
    udang

    ReplyDelete
  3. Grateful, if you could send PMP formulas.
    regards'

    ReplyDelete

Post a Comment

Leave a reply

Popular posts from this blog

26 Proven Work at Home Business Ideas You Can Run Part Time

If you are looking for work at home business ideas, then this list can help you. All of these can be done as part-time business, so you don’t have to leave your job until you are confident of making full time income from your Work at home business.

How to Find Niche Website Ideas for Affiliate Blogs

Choosing right niche website ideas is the most critical decision. The topic of your affiliate blog will have huge impact on the outcome of your efforts over several years.

21 Passive Income Ideas to Achieve Financial Independence

Passive income is the key to achieving financial independence.  Earning Passive income requires you to create some form of asset that can generate income. You might still need some effort to maintain the asset, but it would be significantly less than effort required to build the asset. If you are looking for ideas to generate passive income, than below list of options can help you generate it.