PMP Exam Preparation Notes

Here are note collected during PMP exam preparation.

  • Procurement audit

    A Technique used during procurement closure to find successes and failures that might be useful for other contracts and projects in organization.

  • Monte Carlo Simulation

    is a process used to predict the probability of outcome based on input. Multiple iterations are done with the input value randomly from probability distribution (of input variable) to create probability distribution of the output. Output is generally Total cost or Completion dates. e.g. It can be determined what is the probability of achieving specific total cost or completing project on certain date.

  • Attribute sampling vs.. variable sampling

  • attribute sampling – the result either conforms or does not conform

    variable sampling – the degree to which results conforms

  • Quality Theories

  • Joseph Juran – 80/20 principle, top management involvement, fitness to use

    Edward Deming – 14 steps to total quality management, plan-do-check-act cycle
    Philip Crosby – advocated cost of poor quality, and prevention over inspection, zero defects, quality = conformance to requirement
    Total Quality Management – Theory encourages everybody to continuously find ways to improve quality.

  • Process Analysis

    Quality Assurance tool for process improvement. Recurring Process is checked after certain time for improvements.

  • Std deviation

  • +/-1σ – 68.2%

    +/-2σ – 95.46%
    +/-3σ – 99.73%
    +/-6σ – 99.99%

  • Kaizen - Continuous improvement
  • OPM3

    PMI’s project management maturity model to help organization identify their level of maturity in project management

  • Lessons Learnt are created through out the project and shared. Lessons learnt are finalized in Closing process.
  • RFI – Request for Information is done before RFP, RFQ or IFB is sent to collect information for sellers. The information can be used to select sellers or to create procurement documents.
  • Source Selection Criteria

    Used as guide to select sellers. Sellers can use the criteria to determine the buyer’s need and whether to bid or not.

  • Standard Contract and Special Provisions/Conditions

    Standard Contract are created to be used with standard recurring type of procurement by organization. These can be used without separate legal approval. Special Provisions can be added based on Project requirement and needs legal approval before use.

  • Privity – Contractual relationship
  • Fait Accompli – A negotiating tactic for a must situation such as including meeting government regulations.
  • Type of risks – Business risk (risk of gain or loss); Pure (Insurable risk) – only loss
  • Risk Audit – A monitor and Control risk process to make sure all risks are identified, you have proper response plans etc.
  • Type of performance reports include Status report, Progress report, Trend report, Forecasting report, Variance report, Earned Value report.
  • Resource Histogram

    When are resource needed showing spike in resources. This can help PM arrange resources during peaks.

  • Laissez Fair – A leadership style where people are left alone and manager work as consultant type as required.
  • Reason of conflicts in the order of frequency

  • Schedule

    Project Priorities
    Resources
    Technical Opinion
    Admin procedures
    Cost
    Personality

  • Expectation Theory

    Employees who believe their efforts will lead to effective performance and will be rewarded works productively

  • Arbitration – a neutral party resolve dispute
  • Perquisites or Perks – special benefit
  • Fringe Benefit – Standard benefit everybody gets
  • McGregor’s theory of X and Y

    X = People need to be watched, Y = Opposite

  • Maslow’s Hierarchy of Needs – Lowest to highest

  • Physiology

    Safety
    Social
    Esteem
    Self-fulfillment

  • David McClelland’s Theory of Need or Acquired Need theory

    People are motivated by need for any one of achievement, affiliation, power

  • Herzberg’s Theory

    Poor Hygiene factors may destroy motivation, but improving them will not improve motivation. Motivational factors are work related e.g. Responsibility, Self-actualization, professional growth, work recognition.

  • Phase exists are also known as phase gates, decision gates,stage gates, kill points or milestones.
  • Quality Function deployment

    A type of facilitated workshop technique used in requirement gathering to determine critical characteristics of new product. It starts by Voice of customer (collecting customer needs).

  • Tornado diagram

    A type of Sensitivity analysis (Modelling) technique used in Quantitative risk analysis comparing relative importance and impact of variables.

  • Force majeure - a powerful and unexpected event, such as a hurricane or other disaster
  • Unique organization culture (part of environmental factors) include
  • Shared vision, values, norms, beliefs, expectations

    Policies, methods, procedures
    View of authority relationships
    Work ethics and work hours

  • Cultural differences should be considered when deciding recognition and rewards during develop team process.
  • Accuracy of estimate

  • Rough of order of magnitude – -50% to +50%, generally used in initiating phase

    Budget estimate – -10% to to +25%, generally used in planning
    Definitive estimate – -10% to +10%

  • Activity Attributes – information associated with an activity such as Predecessor, Successor, resources assigned etc.
  • Activity Duration – Time in calendar units.
  • Actual Duration – Time in calendar units between actual start date and current date if activity is not finished
  • Code of Accounts – Numbering system used to identify wbs elements.
  • Cost Performance Baseline – A specific version of time phased budget to compare actual cost to planned cost.
  • Duration – Time in workweeks or workdays.
  • Effort – The number of labor units required to complete schedule activity.
  • Master Schedule – Summary level schedule including major deliverable.
  • Planning Package – WBS Component below control account with known work content but without detailed schedule
  • Project Organization Chart – A chart that shows project team members and their relationships.
  • Project Scope Statement – Contains description of project scope, major deliverables, assumptions, constraints and description of work.
  • Residual Risk – A risk that remains after risk response implementation.
  • Resource Breakdown Structure – A hierarchy chart used to show resources by category and type used for resource levelling.
  • Scope Creep – Adding Scope without approval and without analyzing effect on constraints
  • Secondary Risk – A risk that arises as a result of implementing risk response.
  • Strategies to deal to with risks

  • Negative Risks or threats -

    Avoid – Changing Plan to avoid risks completely example changing schedule or limiting scope.

    Transfer – Transfer risks on someone else e.g. Outsourcing using FP Contract, Insurance etc

    Mitigate – Reducing probability or impact.

    Accept – accept the risk.

    Positive risks or Opportunities -

    Exploit – Reduce the uncertainty of risk happening

    Share – Share the risks with another party who is best able to capture it.

    Enhance – Increase probability or impact of risk

    Accept – Accept but do not actively pursue it.

  • Techniques for resolving conflict

    There are six techniques

    Withdrawing/Avoiding – Retracting from an actual or potential conflict situation.

    Smoothing/Accommodating – Emphasize area of agreement
    Compromising – Alternative where everybody compromises a little.
    Forcing – Pushing one viewpoint
    Collaborating – discussing multiple view point, results in consensus and commitment
    Confronting/Problem Solving – Treating conflict as a potential problem, best method as resolves cause.

  • Five Phases of team building

  • Forming – Initial stage when team is formed and members learn about their roles and responsibilities.

    Storming – The team starts to work on individual tasks. The team is not collaborative yet.
    Norming – The team begins to work together and trust each other.
    Performing – The team functions as a unit and performs as team.
    Adjourning – The team completes the work.

  • Performing Quality Control

  • Cause and Effect diagrams or Ishikawa diagram or Fishbone diagram – shows how factors can be related to effects.

    Control Charts
    Flowcharting
    Histogram – A bar chart showing how often a variable occurs.
    Pareto Chart – A type of histogram showing frequency of occurrence.
    Run Chart – Similar to Control Chart without showing limits
    Scatter diagram – shows relationship between two variables and whether these are related or not.
    Statistical Sampling
    Inspection
    Approved Change Request Review

  • Precision Vs Accuracy

  • Precision is the degree of scatter for repeated measurement. Accuracy is how close the measure value is to expected value.

  • Quality Vs Grade

  • Quality and Grade are different though can be confused. Quality is the degree to which outcome meets the specified requirements and measurements. Grade is the category of the product. For example, Software can have two grades, one with limited features other with all the features.

  • Critical Path Method

  • Critical Path - Critical path is the longest duration path in the network diagram and provides shortest time to complete the project.

    Near Critical Path – The path closest to the critical path. The closer near critical path is to critical path, the more risk to the project. Why? Because if there is need to shorten critical path or lengthen the near critical path, the near critical path will become new critical path.

  • Types of Activity Duration Estimations

  • Analogous Estimating – Uses parameters from similar historical projects to estimate.

    Parametric Estimating – Uses statistical relationship between historical data and variables. Example – cost per labour hour
    Three Point Estimate – PERT (Program Evaluation and Review Technique)E = (O+4M+P)/6
    Heuristic – Rule of Thumb (e.g.. Testing should take 50% of what development takes)  

  • Float(Slack) -

  • Total Float- The amount of time an activity can be delayed without delaying project end date or next milestone.

    Free Float - The amount of time an activity can be delayed without delaying early start of successor activity
    Project Float - The amount of time project can be delayed without delaying promised completion date.Activities on critical path have zero float.
    Float = LS – ES = LF – EF

  • Fast Tracking – Doing Critical path activities in parallel.
  • Crashing – Compressing schedule by increasing cost e.g. Adding resources.
  • Resource Levelling – Limiting resources by compromising schedule and cost to the project.
  • Critical Chain Method – A resource constrained critical path is critical chain. Network diagram is prepared and critical chain is calculated by adding resource dependencies. A buffer is added before milestones to provide cushion.
  • Requirements Traceability Matrix - A table that links requirement to original goal or object or objective to provide traceability.
  • Change Requests and actions

    Actions are taken during projects to mitigate or stop performance deviation.

    Corrective Action – Action taken to bring future performance back to expected performance.

    Preventive Action – Action taken in advance to stop performance to deviate from expected performance.
    Defect Repair – Repair the bug or problem or replace the faulty item

  • Project Documents

    Any document that is not part of project management plan. It includes Project Charter, SOW, Contracts, Stakeholder Register, Risk Register, Issue Log, Change Log, Quality metrics etc.

  • Project Management Information System - Any software tools used in project management process.
  • Change Control System

  • An organizational process asset that includes forms, templates, procedures, software to control, track and monitor changes. This is generally a subset of Configuration management system.

  • Any action that would require change to the project management plan would require a change request. The change can also be requested by stakeholders. Change request would than need to go thru Integrated Change Control Process.
  • Evaluate the impact

    Create options – including Crashing, Fast tracking etc.

    Internally approve the Change request

    Review with management and sponsor

    Review with Customer if required

    Update the status of the in change control system

  • Work Authorization System

  • Work Authorization System is the tool to authorize work performed during Project. It is collection of formally documented procedures to define to ensure work is performed by right resource or team, at appropriate time and proper sequence. The procedures also include required forms, templates, steps and approvals required to perform work,

  • At the beginning of the project there is less cost and less demand for resources. Also there is a higher risk of failure at the beginning of the project. The risk reduces over the life of the project. The stakeholder influence is maximum at the beginning of the project and reduces over the life of the project.
  • Progressive Elaboration means adding more details in an iterative fashion. Project Management Plan is developed using progressive elaboration.
  • Organizational Process Assets

  • Organization Process Assets include all existing documents, templates, Historical information, Lessons learned, plans, procedures, guidelines, risk data etc that can influence project’s success.

  • Enterprise Environmental Factors

  • Enterprise Environmental Factors are unique factors (internal and external) that might impact Project’s success. These are inputs to most Project Management Processes.

    Company Culture and Structure

    Government regulations

    Industry Standards

    Existing Infrastructure

    Existing Resources and Available Skills

    HR Policies

    Market Conditions

    Risk Tolerance

    Political Climate

    Project Management tools

  • Project Life Cycle, Project Phases

  • All projects follow a life cycle from start to close. Generic life cycle can be think of as Starting, Preparing, Executing and Closing.

    Project can have multiple phases. Each Phase is like a new project and goes thru Project Life cycle. Phases would generally have one of the following relationships

    Sequential – New Phase can only start after completing current phase

    Overlapping – New Phase will start before ending current phase.

    Iterative – Only one phase is planned initially and new phase will be planned later as the work continues in the current phase.